2008 Construction Significantly Impacts Campus Parking and Traffic

The loss of surface parking spaces and the occurrence of road closures / detours during the construction will impact daily parking availability and may create a "ripple effect" in other areas of campus as customers relocate to new areas. During this time, motorists should anticipate parking shortages / traffic delays and are encouraged to arrive on campus early. Please view the map and table below for details regarding each summer construction project.


Summer 2008 Construction Projects
#12 John Herrick Drive Resurfacing #11 Parks Hall Lot Resurfacing #16 9th Ave. Garage Elevator Replacement #2 #3 9th Avenue Garage Elevator Replacement #1 #10 9th Avenue East Garage Construction #4 11th Ave. Garage Elevator Replacement #6 College Road Closure #8 Ohio Union North Garage Closed #7 Ohio Union North Garage East Entry/Exit Closure #5 Ohio Union Garage Elevator Replacement #14 Tuttle Park Place Steamline Repair #13 South French Fieldhouse Lot Resurfacing #15 Tuttle Park Place Resurfacing #17 SAS Building Tunnel Project #2 Student Academic Service Building #1 Lane Avenue Parking Garage Construction #9 Arps Garage Repairs

Click the link for a printable version of this map.
For more information, please visit the T&P Calendar of Construction Projects Impacting Traffic and Parking .

Map # Start Date End Date Project (Click on the link for information) Impacts
1,2 4/28/08 12/09 LAPG & SAS Building 400 surface spaces will be lost for construction of 1400 space garage. For remote park and ride options during the construction, please see the Tuttle Shuttle CABS route. Road closures in the area between 9/8 - 9/21 will impact traffic. For more information, please see LAPG Street Closures.
3 4/11/08 6/10/08 9th Ave. Garage Elevator Replacement (#1)
COMPLETED
4 6/10/08 8/22/08 11th Ave. Garage Elevator Replacement Disability spaces will be relocated to ground level.
5 6/09/08 8/29/08 Ohio Union Garage Elevator Replacement Disability spaces will be relocated to ground level.
6 6/09/08 6/30/08 College Road (between 17th & 12th) Closes
COMPLETED
7,8 6/09/08 6/30/08 Ohio Union Garage Construction Please use the Arps Garage or Neil Ave. Garage during this time.
9 6/23/08 9/12/08 Arps Garage Restoration Work 120 spaces will be closed at a given time.
10 6/23/08 8/09/09 9th Ave. Garage East Construction 227 surface spaces will be lost for construction of 997 space garage. For remote park and ride options during the construction, please see the Med Center Express CABS route.
11 6/23/08 7/14/08 Parks Hall Lot Resurfacing
COMPLETED
12 TBA TBA John Herrick Drive Resurfacing Traffic will be reduced to one lane in each direction.
13 6/09/08 7/18/08 South French Field House Repaving
COMPLETED
14 6/23/08 8/29/08 Tuttle Park Place Steam Line Repair Traffic will be rerouted through the Ohio Stadium lots.
15 TBA TBA Tuttle Park Place Repaving
CANCELLED
16 8/24/08 TBA 9th Ave. Garage Elevator Replacement (#2) N/A
17 11/24/08 10/09 SAS Building Tunnel Project N/A
NEW 8/21/08 8/26/08 Neil Ave. Closure Neil Avenue, between Tuttle Park Place and Lane Avenue will close temporarily for road work.


*Please note that all start and end dates are approximate.

For a list of other general construction projects occurring on campus throughout the year, and for information regarding subscribing to the construction project listserv, please visit the General Construction Updates page.